Location: SHARJAH, UAE
Client: JURONG ENGINEERING LIMITED
Earthworks :-
Levelling and compaction of the Sub Grade Soil prior to the application of Road Base. Cutting and filling of soil to reach the desired level.
Area 8500sqm.
Installation Of Kerbstone :-

Supply and Installation of Kerbstone along with the sides of designed inner link road network.

Road Base :-

Supply, Laying & compaction of 400mm Thick crushed Road Base in Two layers.

Asphalt Works :-

Application of 60mm Thick wearing course after spraying Prime Coat.